Shoalwater Bay Training Area Works

Project Overview

Ertech was contracted to repair and remediate the roads and trails assets at Shoalwater Bay Quarry operations. Our responsibilities included maintaining and repairing over 40km of gravel roads, building 6.9km of new embankment, as well as constructing road surfacing and concrete causeways in the Shoalwater Bay Training Area.

Fast Facts

  • ClientDepartment of Defence
  • LocationRockhampton, QLD
  • Year of completion2020

Scope of works

  • Quarry operations to produce re-sheet material and capping
  • Road maintenance (re-grading and re-sheeting) on various sections
  • Reshaping damaged access tracks and re sheet with on-site gravel supply
  • Flood mitigation work
  • Concrete and scour protection work
  • Bulk Earthworks (vertical alignment raise of RD02)
  • Installing traffic furniture (guard rail etc.
  • Drainage (Installing new and clean drains out of existing ones)